Riyadh Metro testing progresses with first lines on course to open in 2021

      Published on Saturday, 12 December , 2020      2689 Views     
Riyadh Metro testing progresses with first lines on course to open in 2021


Timetable tests on lines 4 and 6, respective 30km and 13km overground lines, are currently underway with a view to handing the lines over to the operator, the Flow consortium, comprising Alstom, Hitachi Rail STS, and Italian State Railways (FS), in the second half of the year.




Flow will then simulate network operations ahead of the start of passenger services.

“We are running in what we call carousel mode with 35 trains to simulate the timetable, the maintenance and various other areas,” says Mr Lindsay Vamplew, project director for the Ramped consortium comprising WSP (previously Louis Berger) and Hill International, which is overseeing package three of the project comprising lines 4, 5 and 6.

“At the same time we’re trying to complete the stations, with building systems the last part of that. We are looking for those two lines to go into system demonstration in roughly May and potentially trial running where we handover to the operator to simulate the network in June or July, with a view to getting those two lines running next year.”

The underground 25km Line 5 is running a little further behind. Carousel running is underway, but Vamplew says these trials have not yet reached the stage of replicating the complete service. “It will be September before we go into some of system demonstration and we will look towards the end of the year to handover to the operator,” he says.

Lines 4 and 6 are predominately constructed on an elevated alignment, with some sections of cut and cover tunnel. Photo: RCRC

Work is also progressing on lines 1, 2 and 3, which are similarly in the final 10-12% of the works to be implemented although slightly behind on rolling stock testing, which is not at the carousel stage yet, according to Mr Carter Rohan, project director for the RMTC project management consultancy.

RMTC is made up of Parsons, Egis and Systra, which is overseeing packages 1 and 2 covering lines 1, 2 and 3.

“We’re just starting dynamic testing but we’re not far behind,” Rohan says. “The primary works that we have left on our plate are related to finishing up some of the civils. We’ve got that mostly all complete. But we’re into the mechanical-electrical phase where we’re testing, putting in ventilation and air-conditioning systems, and doing that testing and commissioning. And we’re now focusing on ramping up the signalling, Scada testing, and all the systems related to the role of the rolling stock.”

Work on the $US 24.4bn metro project commenced in April 2014. Riyadh is also developing an integrated city-wide 1900km bus network with around 3000 stops. There are currently 10 million motorised passenger journeys in Riyadh every day, with 80% by private car and only 2% using public transport.



The new public transport network will go a long way to rebalancing this modal split.

Keywords:
Category Lifestyle, Saudi News, Technology | 2020/12/12 latest update at 10:00 AM
Source : Rail Journal | Photocredit : Google
2690 Views
Comments Add comment



Gulf Media

Related Articles

The editorial staff of Saudi Arabia Today would like to give all of its readers from Gulf and Saudi Arabia and the whole world the opportunity to participate actively in the development of the website! If you have something interesting, fun, scandalous - just something worth to be seen from more people. Capture it and share it in the Saudi Arabia Today with a short text.

Do you have information you want to reach our readers?

Send article/s

You can subscribe to our Facebook, Twitter and Google pages or use our RSS feed channel to always read the most important news about Saudi Arabia, the Gulf and the world.


Sponsored Publications